P21114 – Virginia-Daisy Bikeway – Phase 1A

Development & Public Works

P21114 – Virginia-Daisy Bikeway – Phase 1A

This project was awarded to Knife River Corporation – Northwest in the amount of $1,137,113.71 on April 20, 2020.  Questions regarding this project should be directed to the Project Leader.  The original posting is shown below.

Project Leader: Jesse Jones
Phone:  541-736-3720
Email:  jjones@springfield-or.gov

 

Engineers Estimate: Between $1.2 M to $1.5 M

Project Description

Work consists of grind and overlay of existing asphalt roadway, construction of ADA ramps, sidewalks, driveways, a vegetated stormwater planter, raised crosswalks, storm water facilities, speed cushion, landscaping, signage, medians, striping, and other associated features.

View Abridged Bid Book

If the pre-bid meeting is listed as MANDATORY bids will not be accepted from bidders unless it can be confirmed by a signature on the Pre-Bid Meeting Sign-in Sheet that a representative of the organization attended the meeting.

Project Schedule

All dates, times and locations are subject to change

Bid Due/Bid Opening Date and Time March 31, 2020 at 2:00 p.m.
Bid Opening Location Jesse Maine Meeting Room
Pre-Bid Meeting MANDATORY
Pre-Bid Meeting Date and Time March 11, 2020 at 10:00 a.m.
Pre-Bid Meeting Location Jesse Maine Meeting Room
Pre-Bid Meeting Sign-in Sheet View Sign-in Sheet
Deadline for Submission of Questions Prior to Bid Opening March 23, 2020 at Noon
Bid Summary/Notice of Intent to Award View Bid Summary
Anticipated Construction Contract Award April 6, 2020
Anticipated Construction Start May 4, 2020
Project Completion No later than October 16, 2020

All questions regarding this project should be addressed to the Management Support Specialist identified below. Contact with any other City officials may be grounds for disqualification of bid.

Management Support Specialist: Terri White Phone: 541.726.3628 Email: Terri White

Questions will be reviewed and responses will be posted to the Clarification Log at the link below. If, in the opinion of the City, it is necessary to amend or supplement the Invitation to Bid, an Addendum will be prepared, posted below and notifications sent to all bidders that purchased a bid book and those that attended a Pre-bid Informational Meeting and provided a valid e-mail address.

The City will make every reasonable effort to notify all bidders that have purchased a bid book or attended a Pre-bid Informational Meeting of Addenda, however, it is recommended that bidders routinely check the website for updated information. The City is not responsible for any explanation, clarification, interpretation or approval made or given in any manner except by written Addendum issued by the City.

Addenda will not be issued within 72 hours of the bid opening date and time as indicated in the Invitation to Bid without extending the bid opening requirement.

P21114 Clarification Log Last Posted: March 25, 2020

Addenda Issued

Addendum Number Addendum Date Date/Time Posted
#1 03/25/2020 4:50 pm on 03/25/2020